← the whole board
DRAFTEDFROM ANNOUNCED PROJECTS

Storage across the country

64.4 GW is on the board: 10.5 GW testing, 18.5 GW under construction, 15.2 GW permitted, 20.2 GW announced.

Every storage project, biggest first

All 480 projects are listed below.

  • Sunstone SolarOregonPermitted1.2 GWDecember 2027
  • Deschutes Solar and BESSOregonPermitted1.0 GWNovember 2029
  • Libra SolarNevadaUnder construction700 MWDecember 2027
  • Clear Fork Creek Solar and BESS SLFTexasUnder construction600 MWMarch 2027
  • Maricopa SolarArizonaUnder construction550 MWSeptember 2026
  • Bellefield 2 Solar & Energy Storage FarmCaliforniaTesting500 MWDecember 2026
  • Grace Energy CenterCaliforniaPermitted500 MWOctober 2027
  • Hecate Energy Ramsey StorageTexasAnnounced500 MWDecember 2027
  • Hop Hill Solar Generation and BESSWashingtonPermitted500 MWSeptember 2031
  • La Salle ESSTexasAnnounced500 MWJuly 2029
  • Sunscape Renewable EnergyTexasAnnounced500 MWOctober 2028
  • Dutchman Solar generation and BESSWyomingPermitted499 MWJune 2029
  • Snowflake A Solar and BESSArizonaPermitted475 MWAugust 2027
  • Quantum BESSTexasTesting422 MWNovember 2026
  • Quantum II BESSTexasTesting422 MWNovember 2026
  • Tehuacana Creek SolarTexasTesting418 MWDecember 2026
  • Callisto II Energy CenterTexasTesting400 MWNovember 2026
  • CO Bar Solar and BESSArizonaAnnounced400 MWDecember 2027
  • Cowboy Solar IWyomingAnnounced400 MWDecember 2028
  • Eagle Eye Solar and StorageArizonaPermitted400 MWMay 2028
  • GabrielCaliforniaUnder construction400 MWApril 2027
  • Iron BeltTexasAnnounced400 MWJune 2027
  • Lycan Solar ProjectCaliforniaAnnounced400 MWApril 2030
  • MariciCaliforniaUnder construction400 MWJune 2027
  • Pepper Hammock Solar and StorageGeorgiaPermitted400 MWSeptember 2029
  • Purple Sage Energy CenterNevadaAnnounced400 MWNovember 2028
  • Valley Farms Energy CenterArizonaUnder construction400 MWDecember 2027
  • CO Bar D Solar and BESSArizonaAnnounced394 MWMay 2028
  • Arida Solar (Hybrid)NevadaAnnounced370 MWJune 2029
  • Arkansas Cypress Solar StationArkansasAnnounced350 MWJanuary 2029
  • Rowdy Creek Solar and BESSTexasPermitted350 MWMay 2027
  • Cuchillas PV and BESSTexasPermitted307 MWDecember 2028
  • Ash Creek BESSTexasAnnounced306 MWMarch 2028
  • Darden I SolarCaliforniaUnder construction304 MWMarch 2028
  • Darden II SolarCaliforniaUnder construction304 MWMarch 2028
  • Darden III SolarCaliforniaUnder construction304 MWMarch 2028
  • Darden IV SolarCaliforniaUnder construction304 MWMarch 2028
  • Banita Creek- Spindlepop SolarTexasPermitted303 MWApril 2027
  • Desert Sand BESSArizonaPermitted300 MWDecember 2028
  • Easley SolarCaliforniaUnder construction300 MWMarch 2028
  • Elio Energy LLCTexasAnnounced300 MWDecember 2027
  • Humidor Storage ICaliforniaAnnounced300 MWSeptember 2029
  • Lower Snake Solar Generation BESSWashingtonPermitted300 MWOctober 2029
  • O'Bannion Energy StorageTexasUnder construction300 MWDecember 2028
  • Pinopolis BESSSouth CarolinaAnnounced300 MWSeptember 2027
  • Pioneer Clean Energy CenterArizonaUnder construction300 MWApril 2027
  • Red Antelope Solar & Energy Storage FarmArizonaAnnounced300 MWMay 2028
  • Red Butte Solar and StorageUtahPermitted300 MWApril 2029
  • Red EgretTexasUnder construction300 MWOctober 2027
  • Red Hollow Renewable EnergyTexasAnnounced300 MWOctober 2027
  • Roadhouse Energy CenterCaliforniaPermitted300 MWDecember 2027
  • Robinson SolarNevadaAnnounced300 MWDecember 2029
  • Sherco BESSMinnesotaUnder construction300 MWDecember 2027
  • Sherco BESSMinnesotaUnder construction300 MWNovember 2027
  • Southern Bighorn Solar HybridNevadaAnnounced300 MWJuly 2028
  • Sunrose Renewable EnergyTexasAnnounced300 MWDecember 2027
  • THREE SISTERS Solar Generation and BESSArizonaPermitted300 MWApril 2029
  • Vitex StorageNevadaPermitted300 MWJune 2028
  • Elevate MiddletownConnecticutAnnounced275 MWDecember 2027
  • Hashknife Energy Center LLCArizonaTesting275 MWSeptember 2026
  • Royal SlopeWashingtonUnder construction260 MWOctober 2027
  • Hecate Grid East Valley StorageTexasAnnounced255 MWDecember 2027
  • Athens Solar I (Hybrid)CaliforniaAnnounced250 MWJune 2028
  • Dry Land Prairie Energy StorageColoradoUnder construction250 MWDecember 2026
  • Energizar BESSMassachusettsPermitted250 MWSeptember 2027
  • Evlou Solar, LLCTexasUnder construction250 MWJanuary 2028
  • Lazy U ESS 1TexasAnnounced250 MWJuly 2030
  • Lazy U ESS 2TexasAnnounced250 MWJuly 2029
  • Mallard Energy StorageTexasUnder construction250 MWOctober 2026
  • Mystic Springs Renewable Energy (Hybrid)TexasAnnounced250 MWMarch 2028
  • Rock N' RollTexasPermitted250 MWOctober 2027
  • Sawtooth SolarArizonaPermitted250 MWJune 2028
  • South Platte StorageColoradoUnder construction250 MWJune 2027
  • Steel River Solar Phase 1ArkansasUnder construction250 MWAugust 2028
  • Steel River Solar Phase 2ArkansasUnder construction250 MWJuly 2029
  • Steel River Solar Phase 3ArkansasUnder construction250 MWJuly 2030
  • ZeyaTexasUnder construction250 MWSeptember 2026
  • Salmonfly Solar and StorageOregonPermitted247 MWFebruary 2029
  • Pelicans Jaw Hybrid SolarCaliforniaTesting239 MWApril 2027
  • Duffy BESSTexasTesting236 MWDecember 2026
  • Adelite Storage Project LLCTexasUnder construction230 MWMarch 2028
  • Ventures BESSTexasPermitted227 MWSeptember 2028
  • Bramble Energy CenterTexasAnnounced225 MWApril 2029
  • Romero Energy CenterArizonaUnder construction225 MWJune 2027
  • Romero Energy Center II, LLCArizonaUnder construction225 MWJune 2028
  • NISA Electric Generation ProjectNew YorkUnder construction220 MWOctober 2028
  • Amador BESSTexasTesting220 MWApril 2027
  • Coke BESSTexasAnnounced220 MWApril 2028
  • Trenton Channel Energy CenterMichiganTesting220 MWDecember 2026
  • Zeus BESSCaliforniaAnnounced214 MWSeptember 2031
  • Atlas VIIIArizonaTesting210 MWDecember 2026
  • Sanborn Hybrid 3CaliforniaUnder construction210 MWDecember 2026
  • Mule Shoe Energy StorageTexasUnder construction207 MWAugust 2028
  • CO Bar C Solar and BESSArizonaAnnounced206 MWAugust 2027
  • Champaign BESS, LLCTexasAnnounced203 MWJune 2027
  • Dios BESS, LLCTexasAnnounced202 MWMarch 2027
  • Bell Creek BESS LLCTexasAnnounced201 MWNovember 2028
  • Kahla StorageTexasPermitted201 MWDecember 2028
  • Resaca Oasis StorageTexasUnder construction201 MWSeptember 2027
  • Blackcat BESSTexasAnnounced201 MWApril 2028
  • Staccato BESSTexasUnder construction201 MWApril 2027
  • Alamo City ESSTexasAnnounced200 MWJuly 2027
  • Alina Energy LLCTexasAnnounced200 MWJune 2028
  • Anthelope Hills Solar Generation BESSMontanaPermitted200 MWDecember 2027
  • Apache Hill Energy CenterTexasTesting200 MWNovember 2026
  • Avant Prairie ESSTexasAnnounced200 MWJuly 2029
  • Barton Branch IATexasUnder construction200 MWNovember 2026
  • Bee Branch IATexasUnder construction200 MWJune 2027
  • BhaluTexasPermitted200 MWDecember 2027
  • Bravo ESSTexasAnnounced200 MWJuly 2029
  • CastorTexasUnder construction200 MWSeptember 2026
  • Centralia Battery Energy Storage SystemWashingtonPermitted200 MWDecember 2028
  • Cowboy Solar IIWyomingAnnounced200 MWDecember 2027
  • Crawfish Creek Energy StorageAlabamaUnder construction200 MWJune 2029
  • Cumbia Energy CenterTexasAnnounced200 MWSeptember 2027
  • Cypress Harvest Solar StationLouisianaAnnounced200 MWSeptember 2029
  • Dega Solar and StorageAlabamaPermitted200 MWDecember 2029
  • Eldora Energy LLCTexasAnnounced200 MWJuly 2028
  • FlintOhioUnder construction200 MWJuly 2027
  • Greenwater BESSWashingtonTesting200 MWDecember 2026
  • Hashknife Energy Center II LLCArizonaTesting200 MWMarch 2027
  • Hornet Solar II (TX) (Hybrid)TexasPermitted200 MWMarch 2028
  • Jones City 2 SolarTexasUnder construction200 MWMarch 2027
  • Juniper Creek StorageCaliforniaUnder construction200 MWMarch 2028
  • Mendoza Trail BESSTexasTesting200 MWSeptember 2026
  • Metro BESSTexasAnnounced200 MWDecember 2030
  • Morel Energy StorageColoradoUnder construction200 MWDecember 2030
  • Morrow Lake BESSTexasAnnounced200 MWDecember 2029
  • Oakley BESSTexasAnnounced200 MWDecember 2030
  • OCI HillsboroTexasAnnounced200 MWDecember 2027
  • Padua 3TexasTesting200 MWOctober 2026
  • Pine Forest Solar ITexasUnder construction200 MWAugust 2027
  • Pintail BESSTexasTesting200 MWSeptember 2026
  • Prost ESSTexasAnnounced200 MWJuly 2029
  • Rexford 2 Solar FarmCaliforniaAnnounced200 MWDecember 2028
  • Rock Rose Energy StorageTexasUnder construction200 MWMarch 2027
  • Rush ESSTexasAnnounced200 MWDecember 2031
  • Scopus SolarMissouriAnnounced200 MWDecember 2027
  • SE Athos II, LLCCaliforniaUnder construction200 MWJanuary 2027
  • Sienna Solar FarmCaliforniaAnnounced200 MWDecember 2028
  • Solstice Solar LLCOklahomaAnnounced200 MWDecember 2029
  • Sun Angel ESSTexasAnnounced200 MWJuly 2028
  • SunShiner ESSTexasAnnounced200 MWJuly 2029
  • Taft BESSMassachusettsTesting200 MWFebruary 2027
  • Tex-Bar ESSTexasAnnounced200 MWJuly 2029
  • Tidwell Prairie IITexasTesting200 MWOctober 2026
  • Tualatin Battery Energy Storage SystemOregonPermitted200 MWDecember 2027
  • Vertus Energy Storage PlantTexasUnder construction200 MWSeptember 2026
  • Vichy SolarMissouriAnnounced200 MWDecember 2027
  • Willow Creek Energy StorageOklahomaUnder construction200 MWDecember 2026
  • Spindle BESSColoradoTesting199 MWDecember 2026
  • Fremont SolarUtahUnder construction198 MWDecember 2027
  • Bonanza Solar and Storage ProjectNevadaPermitted195 MWDecember 2027
  • Steelhead Energy StorageTexasPermitted194 MWSeptember 2027
  • Harryoung PV and BESSTexasPermitted190 MWMay 2028
  • Key Energy StorageCaliforniaUnder construction190 MWApril 2027
  • Serrano BESSTexasAnnounced186 MWApril 2028
  • Zephyr StorageTexasAnnounced186 MWMarch 2028
  • Arroyo StorageTexasTesting180 MWNovember 2026
  • Brazos River BESS LLCTexasAnnounced180 MWNovember 2028
  • Dawn Break SolarWisconsinPermitted180 MWSeptember 2029
  • Indigo Solar & StorageTexasAnnounced180 MWMay 2027
  • Starr Solar RanchTexasPermitted180 MWDecember 2031
  • Brotherton StorageTexasPermitted176 MWDecember 2027
  • Mcmurtre StorageTexasPermitted176 MWDecember 2027
  • Willis StorageTexasPermitted176 MWSeptember 2027
  • Yooperlite StorageTexasPermitted176 MWDecember 2027
  • Atlas VIIIArizonaTesting172 MWJanuary 2027
  • Country Acres Clean Power LLCCaliforniaTesting172 MWDecember 2026
  • Coneflower Storage Project LLCTexasPermitted171 MWSeptember 2027
  • AGATE BESSWashingtonPermitted170 MWFebruary 2029
  • Salt Cod BESSMassachusettsPermitted168 MWDecember 2028
  • Allen 2 BESSNorth CarolinaAnnounced167 MWJuly 2027
  • Palo Duro Energy Storage IITexasAnnounced166 MWMay 2029
  • Concho Pearl Solar and StorageTexasUnder construction162 MWOctober 2027
  • Dry Creek Energy Storage, LLCCaliforniaUnder construction160 MWNovember 2027
  • Vidal Energy CenterCaliforniaTesting160 MWDecember 2026
  • Pecan BESSTexasPermitted157 MWDecember 2028
  • Chimney Rock BESSTexasAnnounced156 MWApril 2028
  • NY2 BatteryNew YorkPermitted152 MWJuly 2028
  • AgaveArizonaTesting150 MWOctober 2026
  • Atlas BESS IV LLCArizonaTesting150 MWMarch 2027
  • Bellefield 3 Solar and Battery StorageCaliforniaAnnounced150 MWMay 2030
  • Bocanova Energy Storage IITexasTesting150 MWSeptember 2026
  • Boxcar Energy StorageTexasTesting150 MWMay 2027
  • Corazon Energy StorageNew MexicoUnder construction150 MWSeptember 2027
  • Crowned Heron 2 - Storage, LLCTexasTesting150 MWOctober 2026
  • Desert BloomArizonaTesting150 MWSeptember 2026
  • Faraday Energy StorageUtahUnder construction150 MWSeptember 2026
  • Fortress 1ColoradoPermitted150 MWMarch 2028
  • Gale 1 SolarUtahAnnounced150 MWAugust 2030
  • Gunnar Reliability ProjectTexasUnder construction150 MWDecember 2026
  • Mammoth Plains Energy StorageOklahomaAnnounced150 MWNovember 2027
  • Meadow Springs Renewable Energy (Hybrid)IllinoisAnnounced150 MWJune 2028
  • Overnight SolarCaliforniaTesting150 MWJanuary 2027
  • Palo Duro Energy StorageTexasAnnounced150 MWNovember 2027
  • Parks Valley Energy LLCWest VirginiaAnnounced150 MWDecember 2027
  • Santa Teresa SolarNew MexicoTesting150 MWSeptember 2026
  • Selma Energy CenterArizonaUnder construction150 MWDecember 2027
  • Sierra Luna Energy StorageArizonaAnnounced150 MWDecember 2030
  • Carousel Energy Storage, LLCColoradoUnder construction150 MWDecember 2027
  • Chisme Solar and StorageTexasUnder construction146 MWMay 2027
  • Okolona SolarMississippiUnder construction145 MWAugust 2028
  • Summerhill BESSTexasAnnounced143 MWDecember 2028
  • Vial BESSTexasPermitted141 MWSeptember 2027
  • Emmons-Logan Energy StorageNorth DakotaTesting140 MWDecember 2026
  • Blue Lake BESSMinnesotaUnder construction136 MWMay 2027
  • Hecate Grid Gwent Storage 1CaliforniaAnnounced135 MWDecember 2028
  • Stonewall BESSTexasAnnounced135 MWDecember 2029
  • Boulder Solar III LLCNevadaAnnounced128 MWJune 2027
  • Roccasecca BESS LLCNevadaTesting127 MWFebruary 2027
  • Dolomite StorageTexasPermitted126 MWJuly 2028
  • Biglow Solar Generation and BESSOregonPermitted125 MWDecember 2027
  • E W BrownKentuckyTesting125 MWMay 2027
  • Houston County BESSTexasAnnounced125 MWApril 2029
  • OctansTexasUnder construction125 MWDecember 2028
  • Midway BESSCaliforniaUnder construction125 MWJune 2027
  • Lupinus Solar 2, LLCTexasAnnounced123 MWDecember 2027
  • Backbone Creek BESSTexasTesting121 MWDecember 2026
  • Wildcat Ranch Energy StorageTexasAnnounced120 MWNovember 2027
  • Marcos PV and BESSTexasPermitted116 MWAugust 2029
  • Hayrick BESSTexasPermitted114 MWMarch 2028
  • Aratina Solar Center 2CaliforniaTesting113 MWDecember 2026
  • Anode (Springville) BESSCaliforniaTesting113 MWDecember 2026
  • Anode (Springville) BESSCaliforniaTesting113 MWDecember 2026
  • CherryCaliforniaUnder construction110 MWJuly 2027
  • Gatsby Energy Storage ProjectTexasUnder construction103 MWMarch 2027
  • SE Athos II, LLCCaliforniaUnder construction102 MWJanuary 2027
  • SGT Hoskins Solar Project HybridTexasAnnounced102 MWDecember 2027
  • Dolce BESS, LLCTexasAnnounced101 MWApril 2028
  • Mammoth Plains Energy Storage IIOklahomaAnnounced101 MWMay 2029
  • Sandford Solar and StorageTexasPermitted101 MWDecember 2028
  • Hermes Storage BESSTexasTesting100 MWOctober 2026
  • Aramis I Solar ProjectCaliforniaUnder construction100 MWSeptember 2026
  • Buena Vista Energy Center IIINew MexicoUnder construction100 MWDecember 2026
  • Crimson Orchard Solar and BESSIdahoPermitted100 MWApril 2027
  • Dahlia EnergyTexasAnnounced100 MWJune 2028
  • Drennan Energy StorageColoradoPermitted100 MWMarch 2028
  • Four Mile Mesa Solar, LLCNew MexicoUnder construction100 MWJuly 2027
  • Grand Basin Energy StorageMichiganAnnounced100 MWMarch 2027
  • Grand Valley Solar Generation and BESSColoradoPermitted100 MWOctober 2029
  • Holstein 2 Battery StorageTexasAnnounced100 MWMay 2029
  • Imperial Sun SolarCaliforniaPermitted100 MWJuly 2027
  • Kitt SolarArizonaTesting100 MWDecember 2026
  • Northern Divide Energy StorageNorth DakotaTesting100 MWDecember 2026
  • Oso NegroNew MexicoUnder construction100 MWMay 2028
  • Pamela Heights I Energy CenterTexasUnder construction100 MWJanuary 2027
  • Powerline Energy StorageFloridaUnder construction100 MWMarch 2027
  • Raven StorageTexasTesting100 MWNovember 2026
  • Sacramento Valley Energy Center, LLCCaliforniaUnder construction100 MWDecember 2029
  • SE Athos II, LLCCaliforniaUnder construction100 MWJanuary 2027
  • Skylight Renewable EnergyCaliforniaAnnounced100 MWJune 2028
  • Southern Bighorn Solar 2NevadaPermitted100 MWJuly 2028
  • Star Light Energy CenterNew MexicoUnder construction100 MWDecember 2026
  • Stoneridge Solar, LLCTexasTesting100 MWDecember 2026
  • Third Coast BESS, LLCTexasUnder construction100 MWNovember 2027
  • Voyager Energy StorageMichiganTesting100 MWJanuary 2027
  • Weld Energy StorageColoradoTesting100 MWDecember 2026
  • White Tank Energy StorageArizonaUnder construction100 MWMarch 2027
  • Yaupon Solar Project (Hybrid)TexasAnnounced100 MWDecember 2027
  • EdgewaterWisconsinUnder construction99 MWApril 2027
  • Noosa Energy Storage LLCCaliforniaUnder construction99 MWSeptember 2026
  • Cannibal Draw Solar and StorageTexasUnder construction99 MWApril 2028
  • Rosamond South IICaliforniaTesting92 MWNovember 2026
  • Centennial FlatsArizonaUnder construction89 MWSeptember 2026
  • Winchester Solar I, LLCArizonaTesting88 MWMarch 2027
  • Winchester Solar II, LLCArizonaTesting88 MWMay 2027
  • KeamukuHawaiiPermitted86 MWMay 2030
  • Stellar Wright BESSCaliforniaTesting85 MWOctober 2026
  • RedSun PV and BESSTexasPermitted84 MWJuly 2028
  • Lupinus Solar 1, LLCTexasAnnounced83 MWSeptember 2027
  • Big Star Solar, LLC (Hybrid)TexasTesting80 MWOctober 2026
  • Foxtail Flats Solar, LLCNew MexicoUnder construction80 MWMay 2027
  • North Star Energy Storage, LLCMinnesotaUnder construction80 MWApril 2027
  • NISA Electric Generation ProjectNew YorkUnder construction80 MWOctober 2028
  • KCE NY 29, LLCNew YorkAnnounced79 MWMarch 2030
  • Cairos Solar and StorageTexasAnnounced77 MWJune 2027
  • Honeycomb Solar and StorageTexasTesting77 MWNovember 2026
  • Cabokenze Energy StorageGeorgiaAnnounced76 MWNovember 2027
  • Myers Solar and StorageTexasPermitted76 MWAugust 2028
  • Bodkin BESSTexasUnder construction75 MWDecember 2028
  • Boot Hill Energy StorageKansasUnder construction75 MWDecember 2028
  • Key Energy StorageCaliforniaUnder construction75 MWDecember 2026
  • Noria Hondo Solar (Hybrid)TexasPermitted75 MWDecember 2027
  • Zeta Solar & StorageCaliforniaUnder construction75 MWJune 2027
  • Big Fork SolarSouth CarolinaUnder construction75 MWMarch 2027
  • Kingsley Solar FarmCaliforniaAnnounced74 MWDecember 2028
  • Briggs Solar, LLCTexasPermitted71 MWDecember 2027
  • EDPR Scarlet IIICaliforniaTesting70 MWDecember 2026
  • Elevate Pier SCaliforniaPermitted70 MWDecember 2026
  • JVR Energy Park LLCCaliforniaPermitted70 MWMarch 2027
  • Windy Lane Energy CenterNew MexicoUnder construction68 MWDecember 2026
  • Wheatridge Optimization IOregonUnder construction65 MWDecember 2027
  • JasmineCaliforniaTesting64 MWDecember 2027
  • Bird Dog Energy StorageTexasTesting60 MWDecember 2026
  • Wheatridge Optimization IIOregonUnder construction60 MWDecember 2027
  • Iron BESSCaliforniaUnder construction60 MWApril 2027
  • Vaca BESSCaliforniaPermitted60 MWJuly 2027
  • Parowan SolarUtahAnnounced58 MWFebruary 2028
  • HammondGeorgiaTesting58 MWSeptember 2026
  • New Hill 1 BatteryNorth CarolinaUnder construction56 MWSeptember 2027
  • Eagle Springs HybridTexasTesting55 MWDecember 2026
  • Sienna 2 Solar and Storage ProjectCaliforniaAnnounced55 MWMarch 2029
  • Enterprise BESSCaliforniaUnder construction54 MWDecember 2027
  • Gonzaga Ridge Battery FacilityCaliforniaTesting52 MWSeptember 2026
  • Lupinus Storage 3TexasUnder construction51 MWJune 2027
  • Albatross Solar, LLCTexasAnnounced50 MWDecember 2027
  • MRG Goody Solar Project HybridTexasTesting50 MWSeptember 2026
  • Findley PV and BESSTexasPermitted50 MWJanuary 2028
  • Aurora Renewable Energy (Hybrid)CaliforniaAnnounced50 MWApril 2028
  • Baldy Mesa StorageCaliforniaTesting50 MWSeptember 2026
  • Beartooth Energy Storage LLCMontanaPermitted50 MWDecember 2027
  • Dulles Solar and StorageVirginiaTesting50 MWSeptember 2026
  • Elm Flats SolarTexasUnder construction50 MWSeptember 2026
  • FRP Miller SolarFloridaUnder construction50 MWDecember 2026
  • KCE NY 30, LLCNew YorkAnnounced50 MWDecember 2030
  • KCE NY 31, LLCNew YorkAnnounced50 MWMay 2031
  • Kifer BESS 1CaliforniaUnder construction50 MWNovember 2026
  • Lorenzo Energy StorageTexasAnnounced50 MWNovember 2027
  • Maiden Creek BatteryNorth CarolinaUnder construction50 MWJuly 2027
  • Pueblo Airport Generating StationColoradoPermitted50 MWDecember 2027
  • Richwood Solar and StorageOhioAnnounced50 MWDecember 2028
  • Ridgely Energy FarmTennesseeAnnounced50 MWDecember 2029
  • Ryan StorageTexasUnder construction50 MWFebruary 2027
  • Steele Flats Energy StorageNebraskaTesting50 MWDecember 2026
  • Sundance (CO)ColoradoUnder construction50 MWSeptember 2026
  • TREX US Red HollyTexasPermitted50 MWDecember 2027
  • Two Oaks Solar and Storage LLCVirginiaAnnounced50 MWNovember 2027
  • Wildcat Solar Power Plant LLCNew MexicoAnnounced50 MWDecember 2028
  • Fortress 1ColoradoPermitted50 MWMarch 2028
  • Rosamond South IICaliforniaTesting48 MWNovember 2026
  • KCE CT 1, LLCConnecticutAnnounced45 MWApril 2031
  • Dynegy Oakland Power PlantCaliforniaAnnounced43 MWMay 2028
  • Shutler Energy StorageOregonUnder construction41 MWMarch 2028
  • EDPR CA Solar Park VI LLC (CA) HybridCaliforniaTesting40 MWOctober 2026
  • Sunnyside Solar Energy CenterWisconsinTesting40 MWNovember 2026
  • Syracuse and Tours Renewable EnergyCaliforniaUnder construction40 MWNovember 2027
  • Tracy BESSCaliforniaUnder construction40 MWMay 2027
  • Key Energy StorageCaliforniaUnder construction35 MWApril 2027
  • Black Walnut Solar, LLCNorth CarolinaAnnounced32 MWDecember 2028
  • Panther Branch Solar, LLCNorth CarolinaAnnounced32 MWDecember 2029
  • Timber Mill SolarNorth CarolinaAnnounced32 MWDecember 2028
  • Sand Luis WestCaliforniaUnder construction31 MWNovember 2028
  • James River Power StationMissouriUnder construction31 MWJanuary 2027
  • Craggy Energy StorageNorth CarolinaTesting31 MWSeptember 2026
  • AES Waiawa Phase 2 SolarHawaiiTesting30 MWSeptember 2026
  • Rockmont Solar and Storage ProjectNew MexicoPermitted30 MWDecember 2027
  • Second Division SolarTexasPermitted30 MWDecember 2031
  • Robeson Solar INorth CarolinaAnnounced28 MWDecember 2028
  • Arlington Battery Energy Storage SystemWashingtonUnder construction25 MWSeptember 2026
  • ChalanCaliforniaTesting25 MWDecember 2026
  • Glenarm BESS PlantCaliforniaPermitted25 MWJune 2027
  • Solar Star 3CaliforniaTesting23 MWNovember 2026
  • Solar Star 4CaliforniaTesting23 MWNovember 2026
  • Gaskell West Storage 1, LLCCaliforniaTesting22 MWSeptember 2026
  • PF Onsite BESSPennsylvaniaPermitted21 MWJune 2027
  • Bethlehem Energy Center, LLC - (VA)VirginiaUnder construction20 MWOctober 2026
  • Elm City BESSNorth CarolinaTesting20 MWSeptember 2026
  • Evergreen Energy Center, LLCVirginiaTesting20 MWSeptember 2026
  • Honey Creek SolarIndianaAnnounced20 MWDecember 2027
  • KCE NY 10, LLCNew YorkAnnounced20 MWOctober 2028
  • Pace Road Battery StorageFloridaUnder construction20 MWOctober 2027
  • Pure Hedge LLCConnecticutUnder construction20 MWOctober 2027
  • Railroad Energy Center, LLCVirginiaUnder construction20 MWOctober 2026
  • Reid Energy Center, LLCVirginiaUnder construction20 MWDecember 2026
  • South Ripley SolarNew YorkPermitted20 MWDecember 2027
  • Vonore Battery Energy Storage SystemTennesseeUnder construction20 MWDecember 2026
  • Powells Creek Solar - HybridVirginiaAnnounced18 MWJune 2027
  • Asheville BESSNorth CarolinaUnder construction17 MWSeptember 2026
  • Essex VT BESS 1VermontUnder construction16 MWDecember 2026
  • Elevate Arthur KillNew YorkTesting15 MWSeptember 2026
  • Clark Creek Solar PlantNorth CarolinaPermitted14 MWFebruary 2028
  • Milltown Onsite BESSNew JerseyTesting13 MWOctober 2026
  • Gibson Solar Project - HybridCaliforniaUnder construction13 MWDecember 2027
  • ENGIE Solidago Solar Project - HybridDelawareAnnounced13 MWJune 2027
  • Salt City Solar Project - HybridOhioAnnounced13 MWJune 2027
  • Sunnybrook Solar Project - HybridVirginiaAnnounced13 MWJune 2027
  • KRS I Anahola Solar HybridHawaiiAnnounced12 MWJuly 2027
  • KRS II Koloa SolarHawaiiAnnounced12 MWJuly 2027
  • Parkwood BESSNorth CarolinaTesting12 MWDecember 2026
  • Danville VA BESS 2VirginiaUnder construction11 MWOctober 2026
  • Warsaw 2 Energy StorageNorth CarolinaTesting11 MWSeptember 2026
  • Colorado Clean Energy Center (BESS)TexasTesting10 MWDecember 2026
  • Columbus Clean Energy Center (BESS)TexasTesting10 MWNovember 2026
  • Matagorda Clean Energy Center (BESS)TexasTesting10 MWDecember 2026
  • Mesquite Clean Energy Center (BESS)TexasTesting10 MWSeptember 2026
  • Cedar Hill ESSTexasPermitted10 MWJune 2030
  • Grizzly Ridge SolarTexasTesting10 MWSeptember 2026
  • Harlingen #1 BESS 1TexasTesting10 MWNovember 2026
  • Knapp BESSTexasTesting10 MWOctober 2026
  • North Edinburg BESS 1TexasTesting10 MWNovember 2026
  • Orchard BESSTexasTesting10 MWNovember 2026
  • Sherco LDESMinnesotaUnder construction10 MWMay 2028
  • South Portland ESS, LLCMaineUnder construction10 MWDecember 2027
  • Apple BESSTexasTesting10 MWSeptember 2026
  • BESS TX Camarine - BSHOU001TexasUnder construction10 MWNovember 2026
  • HockleyTexasTesting10 MWFebruary 2027
  • Regis LeakeyTexasTesting10 MWDecember 2026
  • Regis MedinaTexasTesting10 MWDecember 2026
  • Torrecillas Energy StorageTexasTesting10 MWDecember 2026
  • Industrial Parkway StorageCaliforniaTesting10 MWSeptember 2026
  • East BernardTexasTesting10 MWNovember 2026
  • PledgerTexasTesting10 MWNovember 2026
  • Sherwood Forest BESSLouisianaAnnounced8 MWJuly 2027
  • Hamakua Energy PlantHawaiiAnnounced8 MWNovember 2030
  • AES Mountain View SolarHawaiiTesting7 MWNovember 2026
  • Puuloa SolarHawaiiAnnounced6 MWNovember 2027
  • Town of Sharon Portfolio -Mt St LandfillMassachusettsTesting6 MWJanuary 2027
  • Bear Valley Battery PlantCaliforniaAnnounced5 MWApril 2027
  • Bensonhurst Energy Storage 1 LLCNew YorkUnder construction5 MWSeptember 2026
  • Borrego - Highland AveMassachusettsUnder construction5 MWNovember 2026
  • Braley Hill North SolarMassachusettsPermitted5 MWMarch 2027
  • Chicopee BESSMassachusettsUnder construction5 MWOctober 2026
  • Framingham BESSMassachusettsUnder construction5 MWOctober 2026
  • Holyoke MA BESS 1MassachusettsUnder construction5 MWSeptember 2026
  • Ipswich MA BESS 1MassachusettsUnder construction5 MWOctober 2026
  • Madena 4CaliforniaPermitted5 MWApril 2027
  • Randall Lane SolarMassachusettsPermitted5 MWMarch 2027
  • Sanford ESS, LLCMaineUnder construction5 MWDecember 2027
  • SV CSG BloomingtonIllinoisUnder construction5 MWAugust 2027
  • SV CSG MantenoIllinoisUnder construction5 MWAugust 2027
  • Blue Aster B Clean Energy LLCNew YorkUnder construction5 MWAugust 2027
  • Blue Aster C Clean Energy LLCNew YorkUnder construction5 MWAugust 2027
  • Blue Aster Clean Energy LLCNew YorkUnder construction5 MWAugust 2027
  • Heron Clean Energy, LLCNew YorkUnder construction5 MWDecember 2026
  • Jamaica Community Energy, LLCNew YorkUnder construction5 MWJanuary 2027
  • Lobelia 4452 Clean Energy LLCNew YorkUnder construction5 MWJuly 2027
  • Lobelia Clean Energy LLCNew YorkUnder construction5 MWJuly 2027
  • Wintergreen B Clean Energy LLCNew YorkUnder construction5 MWJuly 2027
  • Wintergreen C Clean Energy LLCNew YorkUnder construction5 MWJuly 2027
  • Wintergreen Clean Energy, LLCNew YorkUnder construction5 MWJuly 2027
  • Wintergreen D Clean Energy LLCNew YorkUnder construction5 MWJuly 2027
  • Longtown Energy StorageSouth CarolinaTesting5 MWSeptember 2026
  • Eastern BlueBird Clean Energy LLCNew YorkUnder construction4 MWJune 2027
  • Northern Cardinal Clean Energy, LLCNew YorkUnder construction4 MWJune 2027
  • Riverhead - CVENew YorkUnder construction4 MWSeptember 2026
  • Snipatuit Road SolarMassachusettsPermitted4 MWMarch 2027
  • Madena 3CaliforniaTesting4 MWJanuary 2027
  • MCCo BESS Generating FacilityOhioTesting4 MWOctober 2026
  • MCCo BESS Generating FacilityOhioTesting4 MWOctober 2026
  • MCCo BESS Generating FacilityOhioTesting4 MWOctober 2026
  • MCCo BESS Generating FacilityOhioTesting4 MWOctober 2026
  • Tanglewood BESSNorth CarolinaTesting4 MWDecember 2026
  • Water Willow A Clean Energy LLCNew YorkUnder construction4 MWApril 2027
  • Water Willow B Clean Energy LLCNew YorkUnder construction4 MWApril 2027
  • Windsor BESSNorth CarolinaTesting4 MWDecember 2026
  • Coral Honeysuckle Clean Energy LLCNew YorkTesting4 MWMarch 2027
  • Linden Clean Energy, LLCNew YorkTesting4 MWMarch 2027
  • Roseate Tern Clean Energy LLCNew YorkUnder construction3 MWAugust 2027
  • Cushman Road SolarMassachusettsPermitted3 MWMay 2027
  • EnerSmart Mesa Heights Sub StationCaliforniaUnder construction3 MWDecember 2026
  • Gardenia 1CaliforniaAnnounced3 MWJune 2027
  • Merced BESSCaliforniaTesting3 MWSeptember 2026
  • Nebo Energy StorageNorth CarolinaUnder construction3 MWOctober 2026
  • NL NY- PulaskiNew YorkTesting3 MWSeptember 2026
  • Redlands DC 9 - sline609CaliforniaUnder construction2 MWNovember 2026
  • Piping Plover Clean Energy, LLCNew YorkUnder construction2 MWApril 2027
  • Warbler Clean Energy LLCNew YorkUnder construction2 MWApril 2027
  • CA Riverside 2356 Fleetwood Dr.CaliforniaTesting2 MWNovember 2026
  • MA Acushnet 540R Main StMassachusettsPermitted2 MWMarch 2027
  • Merced 2 BESSCaliforniaTesting2 MWSeptember 2026
  • OIT BESSOregonUnder construction2 MWDecember 2027
  • Six Flags Magic MountainCaliforniaTesting2 MWSeptember 2026
  • Solar Carver 1 HybridMassachusettsTesting2 MWOctober 2026
  • CA Bloomington 2551 S Lilac Avenue MicroCaliforniaTesting2 MWNovember 2026
  • Jade Solar 3CaliforniaAnnounced2 MWJune 2027
  • Cambridge CT HybridMinnesotaUnder construction1 MWDecember 2027
  • East Road Storage ProjectCaliforniaUnder construction1 MWJune 2027
  • Featherbed Lane South SolarMassachusettsPermitted1 MWMarch 2027
  • Solar Carver 3 HybridMassachusettsTesting1 MWOctober 2026
  • Manorville IINew YorkPermitted1 MWDecember 2027
  • Bishop Ranch - BR 3-FFCaliforniaTesting1 MWJuly 2027
  • Bishop Ranch - BR 3-GGCaliforniaTesting1 MWJuly 2027
  • Bishop Ranch - BR 3-HHCaliforniaTesting1 MWJuly 2027
  • Las Virgenes MWD - Composting PlantCaliforniaTesting1 MWOctober 2026
  • Romeoville 34 - SLCHI234 - BSCHI234IllinoisUnder construction1 MWMay 2027
  • Sanger USD - Sanger West HSCaliforniaTesting1 MWOctober 2026
  • Bakersfield DriverCaliforniaTesting0 MWSeptember 2026
  • Palmdale Water District 6MG TankCaliforniaTesting0 MWNovember 2026
  • Pivot Energy PPA 29 LLCCaliforniaTesting0 MWNovember 2026

Capacity is shown in megawatts (MW). Planned dates come from EIA and may change with later updates. We do not independently verify those dates or estimate each project’s likelihood of completion.

EIA-860M · workbook read October 2026