Florida
Natural gas accounted for 73% of generation in Florida over the 12 months to July 2026.
Where they are
Every announced project in Florida with a recorded location; 37 sites.
Natural gas73%Solar12%Nuclear10%Coal4%Other (<2.5% each)0%
| Fuel | GWh | Share | YoY |
|---|---|---|---|
| Natural gas | 197,708 | 72.9% | ↓ 2.1 |
| Solar | 32,598 | 12.0% | ↑ 1.8 |
| Nuclear | 27,866 | 10.3% | ↓ 0.7 |
| Coal | 11,969 | 4.4% | ↑ 1.2 |
| Other | 984 | 0.4% | ↓ 0.1 |
| Hydro | 38 | 0.0% | ↓ 0.1 |
What’s standing
The 8 largest of 751 operating generators; 81.0 GW total capacity.
- St LucieNuclear · Florida Power & Light Co1.1 GW1976
- St LucieNuclear · Florida Power & Light Co1.1 GW1983
- Turkey PointNuclear · Florida Power & Light Co0.9 GW1972
- Turkey PointNuclear · Florida Power & Light Co0.9 GW1973
- ManateeNatural gas · Florida Power & Light Co0.9 GW1976
- ManateeNatural gas · Florida Power & Light Co0.9 GW1977
- Crystal RiverCoal · Duke Energy Florida, LLC0.7 GW1984
- Crystal RiverCoal · Duke Energy Florida, LLC0.7 GW1982
On the drawing board
Florida has 81.0 GW standing. Another 1.1 GW is on the board by 2026: 0.8 GW testing, 0.3 GW under construction.
- Shady Hills Combined Cycle FacilityTesting612 MW2026
- Keene Branch SolarTesting75 MW2026
- Brewster SolarUnder construction40 MW2026
- Mattaniah SolarUnder construction52 MW2026
- FRP Forest Trail SolarUnder construction50 MW2026
- FRP Miller SolarUnder construction75 MW2026
- Highland Solar SouthTesting75 MW2026
- Bailey Mill SolarTesting75 MW2026
- BayboroRetiring57 MW2026
- BayboroRetiring57 MW2026
- BayboroRetiring57 MW2026
Battery storage
- FRP Miller SolarUnder construction50 MW2026
Florida's announced projects could add 6.6 TWh a year by 2031. Our projection includes 6.3 TWh after applying completion factors based on project status.